Previous Projects
Pre-Engineered Metal Building Erection
Buffalo, NY
Celtic was contracted to erect a new PEMB for Fleet Maintenance Inc. Work included:
- Complete erection of the 12,000-sf high bay service building.
- Erected all structural steel, and installed all roof panels, siding, insulation, exterior door openings, and gutters/downspouts,
- Full interior buildout, including offices, bathroom, breakrooms, and mezzanine.
- Project was safely completed ahead of schedule.
Pre-Engineered Metal Building Erection
Buffalo, NY
Celtic was contracted to erect multiple new PEMB’s for Buffalo Transportation. Work included:
- Complete erection of multiple high bay PEMB’s totaling over 20,000-sf.
- Since these buildings were additions to an existing structure, complete flashing & tie ins to existing buildings was required.
- Erected all structural steel, and installed all roof panels, siding, insulation, exterior door openings, and gutters/downspouts,
- Full interior buildout, including offices, bathrooms, breakrooms.
- Project was safely completed ahead of schedule.
Design & Construction of New Warehouse Building
Depew, NY
Celtic was contracted to design and construct a new warehouse building for Jim Murphy Buick GMC. Work included:
- Complete design, engineering, and planning for the new structure.
- Worked with town to get through the zoning, planning, and permit processes.
- Complete construction of the new 5,000-sf warehouse building.
- Erected all structural members, and installed all roof panels, siding, insulation, exterior OH doors, concrete slab & foundations.
- Full interior buildout.
Pre-Engineered Metal Building Erection
West Seneca, NY
Celtic was contracted to erect a new bottling facility for Mayer Brothers Beverages. Work included:
- Complete erection of the 5,000-sf bottling building.
- Erected all structural steel, and installed all roof panels, siding, insulation, exterior door openings, and gutters/downspouts,
- Building was safely constructed in an area surrounded by operating process lines, equipment, and vessels, with zero disruption to ongoing operations.
- Full interior buildout, including dock levelers and full liner panel.
- Project was safely completed ahead of schedule.
Data Center Construction
Niagara Falls, NY
Celtic was contracted to perform a complete construction of Data Mining Halls in a facility located in Niagara Falls, NY. Work included the installation of 14+ garage doors, constructing a new switchyard, and designing and installing 5 air ventilation penthouses. Work was performed safely and efficiently, with minimal disruption to facility operations. All work was completed over a live operating facility, including hundreds of operating miners directly below the work area.
Processing Plant Erection
Lackawanna, NY
Structural Steel & Major Equipment Erection
-
Complete erection of all required structural steel for a sugar refining plant.
-
Safely and efficiently installed over 100 structural steel beams, spanning 5 floors and reaching heights in excess of 115 ft.
-
Surgical demolition of original steel beams to allow for tie-ins to the existing building.
-
Rigged and placed all major equipment for the facility. Major equipment included 3 Strike Receivers (28,000 Lbs.), 3 Condensers (22,000 lbs.), and 3 Vacuum Pans (70,000 Lbs.).
-
Vacuum Pans came in many pieces and required complete construction and welding on the ground level.
-
Celtic safely worked around the clock to complete the project within owner’s requested timeline.
Structural Reinforcement
Lockport, NY
Celtic was contracted to perform a Structural Reinforcement for a site in Lockport, NY. Work included the installation of new steel columns and selecting roof purlins to stabilize the structure. Additionally, our team designed and fabricated 45-degree steel supports to help transfer roof loads to new support columns. Without disrupting plant production, Celtic removed and replaced all structural support columns for the active Plant Load Out Building and completed the project safely ahead of schedule.
Spray Foam & Industial Coatings
Buffalo, NY
Celtic was contracted to perform a Spray Foam & Industial Coatings for a site in Buffalo, NY. Work included:
-
Sprayed entire 80,000 sf roof with 1.5” of 4 lb. SPF roofing foam.
-
Coated entire roof with 2 coats of SI-92 Silicone Coating for weather
protection.
-
Sprayed over 35,000sf of exterior brick walls with closed cell foam. Covered all foam with tinted exterior coating for weather protection.
-
Sprayed over 80,000sf or interior ceilings, and 90,000 sf of interior walls with open cell foam for insulation and sound mitigation.
-
Coated all interior walls and ceilings with DC315 Fireproof coating to comply with all building codes.
Structural Replacement
Buffalo, NY
Celtic was contracted to perform a Structural Replacement for a site in Buffalo, NY. Work included:
-
Removed over 60 damaged roof sections.
-
Replaced all structural members that were damaged from corrosion and
section loss.
-
Installed new structural members and roof decking to over 60 roof sections.
-
Installed all new steel columns and selected roof purlins to stabilize structure.
-
Project was safely completed ahead of schedule.
CIVIL/SITE WORK
Niagara Falls, NY
Celtic was contracted to perform Civil/Site work for a site in Niagara Falls, NY. Work included:
-
Complete site grading and backfill of the 40,000-sf area.
-
Design and construction of 18 concrete pads to support the modified
mobile mining units.
-
Design and construction of 18 transformer pads, and 3 switchgear pads to support all electrical equipment.
-
All trenching, backfill, and concrete work required for underground electrical services to the containers.
-
All rigging and crane work required to unload and place the 18 mobile mining containers, 18 transformers, and 3 switchgears.
-
Work was safely and successfully completed ahead of schedule.